SR / EN
GSS - Global Substation Solutions

CONSULTING

CONSULTING

We provide consulting services according to international standards and procedures, accepted by investors and financial institutions, on power engineering facility projects.

2017
  • Consulting services: supervision of replacement of two existing step-up transformers - Markabi Power Plant, Lebanon. Client: MML Middle East Ltd Dubai.
  • Accredited engineer consulting services for DEWA (UAE) – transformer specialist, supervision of repeated factory acceptance tests of 50MVA 132/11kV transformer. Client: MML Middle East Ltd Dubai.
  • Engineering and consulting services: Preparation of test plans, Master Test Plan and Site Acceptance Test Plan. Client: IMES Engineering & Contracting Ltd, UK.
2016
  • Consulting services: supervision of transformer replacement - Markabi Power Plant, Lebanon.
  • Consulting for feasibility study and general projects for 400kV OHL Bajina Basta – Kraljevo 3 as part of the trans-Balkan corridor.
2015
  • Consulting for feasibility study and conceptual design for CGES transmission network expansion for renewable energy development, Montenegro.
2013
  • Consulting services project Albania – Feasibility Study – 220kV OHL Elbasan 1 – Fieri.